FESCO New Connection: Online Application & Demand Notice 2023

FESCO New Connection

Do you want to transfer your electricity meter or install a new FESCO connection? Faisalabad Electric Supply Company has made the procedure much easier and smoother. Now, you can visit the nearest Customer Care Center or apply online for a FESCO new connection for a domestic, commercial, or agricultural connection. So, let’s explore how you can apply for a new FESCO connection in a few simple, quick, and easy steps!

Also Check: FESCO Duplicate Bill Online

FESCO New Connection Application Form and Step-by-Step Procedure

The online system has facilitated FESCO consumers to acquire a new electricity connection by following simple steps. Now, you don’t need to frequently visit FESCO Customer Care Center to request or know the proceeding of your application. Rather, you can apply for a new meter as well as track FESCO new connection status online with a few clicks. Below is the step-by-step procedure to download FESCO new connection form online and the complete procedure. So, let’s have a look!

  • FESCO consumers can download the application form from the official website at http://fesco.com.pk/ or Visit the ‘Electricity New Connection’ Online Portal at http://www.enc.com.pk/.
  • Multiple options are available on the left side of the display, including ‘Online Application, Change of Connection Name, Print form/ Demand Notice (DN), Pay and Upload Demand Notice.’ You can choose the option as per your requirement.
  • Click the ‘Apply’ tab to open an online form, where you will provide your Neighbor’s Reference Number, Distribution Company (FESCO), Category Type (Load Requirement), and Subdivision.
  • After completing this online form, another comprehensive New Connection Application form will appear on the screen. There’re 5 sections of this online new meter connection form comprising the Applicant’s particulars, Contact information, Details of the premises, and required documents.
New FESCO Connection Application Form

1- Fill the Applicant’s Particulars’ Section

Choose the Connection type per your need, such as Domestic, Commercial, Agricultural, Industrial, etc. Next, enter your name, CNIC, Address, Mobile Number, and Father/Husband’s name. Select Landlord/Owner if you are a real property owner and Tenant if you need a new electricity connection on a Rent property.

2- Contact Person Information

Next, you will add the Contact Person Information, i.e., the person other than the applicant to be contacted. In this section, you will provide the contact person’s name, mobile number, Email, and present address.

3- Premises Detail

In the last, add the details about the number of meters already installed in that location, minimum load, and address of the premises.

4- Upload Documents

Upload the required documents in JPG or PDF, with an image size of 300KB. The documents include Property Ownership, Attested copies of the CNIC of the applicant and the Witness, the Neighbor’s duplicate FESCO bill copy, and the Wiring Contractor’s Test Report.

5- Terms and Conditions

Read the ‘Terms and Conditions’ section of the DISCO written at the end of the application form and press the ‘Agree’ icon. Fill in the Captcha field and submit the FESCO online Application Form.

Apply and Track New Connection Via ENC Portal

FESCO New Connection Tracking

After completing the application form, applicants receive a FESCO new connection application tracking number. You can use this tracking I’d later to track your application proceedings. Follow the below-mentioned quick and easy steps to track your online FESCO new connection application:

  • Apply the ‘Track’ tab displayed on the ENC Portal. Two options will be displayed on the screen to depict whether you’re applying for a FESCO New Connection’ or ‘Change of Name/ Tariff/Load. Choose the first option to track your meter connection application.
  • Select ‘FESCO’ as your Electricity Distribution Company from the drop-down menu and enter your Tracking I’d or CNIC.
  • Your application status will be displayed on the screen showing the estimated time frame or workflow required to complete the installation process.

New Connection Application Procedure in Urdu

New Connection FESCO 
Application Procedure in Urdu

Documents Required for Residential Connections

  • Attested copies of the CNIC of the applicant and Witnesses
  • Ownership Certificate
  • Affidavit by the owner on non-judicial stamp paper
  • Applicant’s Undertaking
  • NOC for tenant ownership

Documents Required for the Commercial Connections

  • Attested copies of the CNIC of the directors.
  • The ‘Charge Creation Certificate’, issued by the SECP (Security and Exchange Commission of Pakistan).
  • An ‘Incorporation Certificate’ for private limited companies.
  • Sitemap where the new connection will be installed.
  • Power of attorney in case of more than one owner of the property.
  • The NOC on the company letterhead.

Issuance of ENC Demand Notice

The FESCO ENC team will evaluate your application and enlist the requirements for installing a new meter, such as conductors, service lines, and other supplies. Within 15 days of receiving your application, ENC will provide you with a Demand Notice.

Procedure to Download or Print FESCO Demand Notice

If your application tracking shows the status of your application as ‘Completed or Pay Demand Notice,’ then you will download or print the form by the below-mentioned simple steps:

  • Again visit the ENC Portal’s Homepage, carrying all the available options and click the ‘Print DN (Demand Notice)’ option.
  • Choose your application type as ‘New Connection’ and enter your Tracking I’d or CNIC. The download or print options will be displayed along with the Demand Notice. Click on the required field, i.e., the ‘Download’ or ‘Print’ option.
  • Submit the FESCO Demand Notice fee in the nearest bank or online within the due date and upload the scanned DN in the ENC Portal for further action.

FESCO New Meter Connection Fee 2023

The FESCO New Connection Demand Notice fee depends on fixed and variable charges for a new electricity connection. Usually, it depends on the connection type, i.e., single or 3-phase connection and the length of the service line. For more information, view the updated FESCO new connection charges (16-1-2023) in the table shown below:

For Single-Phase Connection

DescriptionNew Connection Charges
Length of Service Line upto 40 meters.Rs. 9000/-
Length of Service Line from above 40 to 100 meters (one span LT with Ant-Conductor and One Pole).Rs. 9000+800/meter above 40 meters Length of Service Line.
Length of Service Line from above 100 to 160 meters (2 spans LT with Ant-Conductor and two Poles)Rs. 57,000+1000/meter above 100 meters Length of Service Line.

For Three- Phase Connection

DescriptionNew Connection Charges
Length of Service Line upto 40 meters.Rs. 35,000/
Length of Service Line from above 40 to 100 meters (one span LT with Ant-Conductor and One Pole).Rs. 35,000+1000 per meter above 40 meters Length of Service Line.
Length of Service Line from above 100 to 160 meters (2 spans LT with Ant-Conductor and two Poles)Rs. 95,000+1100 per meter above 100 meters Length of Service Line.
Length of Service Line from above 160 to 280 meters.Rs. 161,000+1200 per meter above 160 meters Length of Service Line.

How to Upload FESCO Demand Notice Online?

Submitting the Demand Notice through ENC involves a few simple steps described below:

  • Click the ‘Upload DN’ tab on the ENC Portal’s display. Choose the new connection option and enter your Tracking Number or CNIC in the input fields.
  • Upload the scanned copy of the Demand Notice and click the save icon to keep it for future records.

Expected Time-Frame for a New FESCO Connection

Category-1: Load Up to 15 kW at 400 V

ProcedureConcerned StaffTime-frame/Days
Application Submission to the concerned Sub-divisionSDC, LS, SDOHead Draft man/XEN/DMO4
Issuance of Demand Notice after documents’ verificationLS, SDO/AMOHead Draft man/XEN/DMO6
Approval of Store Requisition by SCOLS, SDO/AMOXEN/DMO11
Meter InstallationLSSDO/AMOXEN/DMO9
Total Required Days 30

Category-2: Load more than 15 kW and upto 70 kW at 400 V

ProcedureConcerned StaffTime-frame/Days
Application Submission to the concerned Sub-divisionHead Draft man/XEN/DMO5
Issuance of Demand Notice after documents’ verificationXEN/DMO8
Approval of Store Requisition by SCOXEN/DMO25
Meter InstallationSDO/AMOXEN/DMOXEN/DM (M& T)15
Total Required Days 53

Category-3: Load more than 70 kW and upto 500 kW at 400 V

ProcedureConcerned StaffTime-frame/Days
Application Submission to the concerned Sub-divisionHead Draft man/SE/Manager (O)6
Issuance of Demand Notice after documents’ verificationSE/Manager (O)10
Approval of Store Requisition by SCOPD (Construction)XEN/DMO20
Meter InstallationSDO/AMOXEN/DM (M& T)XEN/DMOXEN/DM (M& T)37
Total Required Days 73

Category-4: Load Above 500 kW and upto 5000 kW at 11KV or 33 KV

ProcedureConcerned StaffTime-frame/Days
Application Submission to the concerned Sub-divisionManager (P& E)10
Issuance of Demand Notice after documents’ verificationManager (P& E)20
Approval of Store Requisition by SCOPD (Construction)XEN/DMO55
Meter InstallationSE Manager (O)Manager (M& T)XEN/DMOXEN/DM (M& T)21
Total Required Days 106

Category-5: All Loads at 66KV or above

ProcedureConcerned StaffTime-frame/Days
Application Submission to the concerned CEOManager (P& E)30
Issuance of Demand Notice after documents’ verificationCE (T & G)CEO OfficeMD, NTDC15
Approval of Store Requisition by SCOCEOCE (T&G)PD (GSC)411
Meter InstallationManager (P & E)Manager (M & T)SE/Manager (O)XEN/DM40
Total Required Days 496

Bottom Line

The online system has facilitated the FESCO new Connection application procedure much easier and hassle-free. Now, you can quickly track the new connection application status, download the online form, or take its printout in just a few minutes. For more information or queries, you can contact us 24/7. Our team is always available to assist you with your electricity-related problems.

Similar Posts